Hi guys!
First off I want to say THANK YOU to everyone who has donated to Classic Hall. We have raised enough money to secure our $1,085,500 grant from the Mabee Foundation for Classic!!! We aren’t quite finished with the campaign yet, so if you haven’t given yet, there is still an opportunity. BUT, we met that goal, which is fantastic. (full press release)
Secondly, I wanted to do quick post about what’s been happening with Classic in the last 30 days. I don’t have any new pictures at the moment because you have seen most of what’s been going on. Most of the work is stuff I can’t show you easily, but progress is being made. Here is the “official” list of stuff that’s been happening:
- Geothermal well drilling is complete
- The steam tunnel has been removed and capped back in front of Givens
- North set of stairs has been removed and re-poured
- Leveled the slope on the South end of the building
- Interior demolition continues with the removal of the stairwell cap
- Excavation for interior footings in the 1st floor basement and the elevator pit area
- Floor joist bracing with LVL beams (laminated veneer lumber) on the floor joists
If you ever have any questions stick them in the comments and I will do the best I can to find the answers! Until next time…
-jenny